Removal and compressor installation. Nissan Almera (from 1995 to 1999 of release)
Nissan Almera service from 1995 to 2000 in N15 body
1. General information
2. The general requirements to car repairs
3. Operation and car maintenance
4. Petrol engines
5. Diesel engines
6. Transmission
7. Running gear
8. Steering
9. Brake system
10. Electric equipment
11. Body
11.1. Main data
11.2. Body repair
11.3. Heating and ventilation system
11.4. Climatic installation (conditioner)
11.4.1. Filling of climatic installation
11.4.2. Removal and compressor installation
11.4.3. Removal and installation of a belt of a drive of the compressor
11.4.4. Removal and installation of a protective casing of the evaporator
11.5. System of safety cushions and prednatyazhitel of seat belts
12. Appendices
13. Electric equipment schemes
 









993f9bf4 993f9bf4 993f9bf4

11-4-2-snyatie-i-ustanovka-kompressora.html

11.4.2. Removal and compressor installation


Fig. 9.48. Fastening of the compressor of the conditioner: And — GA14DE and GA16DE engines; B — the CD20 engine (3 bolts + 1 top bolt which in drawing is not visible)



Disconnect minus a wire from the storage battery. Lift and establish on supports a forward part of the car. Pump out a coolant from central air. Remove a driving belt of the compressor (see below). Unscrew unions on the pipelines suitable to the compressor, then muffle pipelines and compressor openings by means of the corresponding jams. Separate the socket of the coupling of the compressor, then a temperature-sensitive element. Turn out bolts of fastening of the compressor (fig. 9.48) and take out the compressor from below.
Installation make in sequence, return to removal. Thus replace all sealing rings and a dehumidifier. Replace oil in a compressor case. Fill with a coolant central air. Be convinced of absence of leakage of a coolant and operability of the conditioner.


«previous page
11.4.1. Filling of climatic installation
following page»
11.4.3. Removal and installation of a belt of a drive of the compressor